Tag: Gym construction

Gym Floor is DONE!!

June 10, 2018 / ziegelbaur

It took pretty much the month of May to complete the gym floor. There were 9 strips poured in all. It was most challenging when it rained — which was only a couple of times. Still, the surface is looking …

Report This Post

Gym Construction – April 2018 update

April 27, 2018 / ziegelbaur

“What’s been happening on the gym construction this month,” you ask?

Lots. For starters, some frames are in the windows on the building part.

They made and installed trusses for the roof over the office and fitness room. Ron’s hoping …

Report This Post

Gym Roof Done and Celebrated!

March 31, 2018 / ziegelbaur

The first week of March, the first side of the roof was almost completed.

The 2nd week of March the other side of the roof was begun — notice you can see blue sky through the clear skylight roofing sheets.…

Report This Post

Gym Roof Progress

February 28, 2018 / ziegelbaur

February 2018 found the roofing material going up on the new gym!

Guys on the ground wait to hoist up the sheets of roofing.

 

Each sheet is screwed in place

We’re thankful for safety of the rew working at …

Report This Post

Busy Day in Construction — Part 3

January 21, 2018 / ziegelbaur

Friday the 19th January was a very busy day for Ron and the guys working on the gym construction project. The big crane came for the last time.

With the trusses all raised into position for the gym roof, Ron …

Report This Post

Busy Day in Construction — Part 2

January 21, 2018 / ziegelbaur

Friday the 19th January was a very busy day for Ron and the guys working on the gym construction project. The big crane came for the last time.

Smaller and lighter, these went up much faster than the central trusses.…

Report This Post

Busy Day in Construcion — Part 1

January 20, 2018 / ziegelbaur

Friday the 19th January was a very busy day for Ron and the guys working on the gym construction project. The big crane came for the last time.

This last, broken, fixed (or so we thought) truss was lifted slowly …

Report This Post

Raise the Trusses

January 6, 2018 / ziegelbaur

January 3, 4 and 5 big progress happened on the gym construction. The biggest crate yet came to lift the trusses up on top of the support beams.

The workers on scaffolding helped the tabs fit into the slots like …

Report This Post

Trusses: Some Assembly Required

December 16, 2017 / ziegelbaur

December 15th a crane was hired to come assist in the assembly of the trusses for the covered gym.

Every part of every truss was welded by Zacharie. He is proud of his work, and he helped construction foreman assemble …

Report This Post

Stairway to Fitness

November 11, 2017 / ziegelbaur

Since the upper floor was poured in July, the only way up was by ladder (on the right in the photo above). On October 26 that all changed. Lower stairs were filled in by shovels.

The top steps were filled …

Report This Post

Posts pagination

1 2 Next »

Recent Posts

  • Cameroon Labor Day Holiday
  • A New Science Lab
  • Carnival at Rain Forest
  • Easter Sunrise Service
  • Season Finale Storms

Blogs of Africa Mission Friends

  • Jeff & Carolyn Stoker
  • Josh & Lori Shinar
  • Karl & Mary Noren
  • Pete & Cindy Ekstrand
  • Roy & Aleta Danforth
  • Tim & Helen Smith
  • UBAC Hostel Construction

Favorite Web Sites

  • 1st Covenant Church GR, MI
  • Evangelical Covenant Church
  • Rain Forest International School
  • Ron & Janet Ziegelbaur on Facebook
  • Women At Risk International

Categories

Tags

climbing wall Gym construction Patience Retaining Wall RFIS Events & Activities Ruth & Gabrielle

Archives

Powered by WordPress | Theme by Themehaus

Report This Blog